UNSW Paddington Goods Lift Removal

Lift Removal
Education
Overhead Traction
UNSW
ERS partnered with Liftronic in November 2017 to help with a Lift Replacement Project on a large goods Lift including installing an engineered large lifting beam, removing the existing lift and motor room gear, Full ripout and make good
1

Total Lifts

4

Total Floors

Project Summary

Contractor – Liftronic
Project Manager – Wayne Campbell
Project Site – UNSW Paddington
Project Date – Nov 2017
Project Scope Includes:

  • Complete Removal of 1×4 Stop OHT Lift
  • Provide and Install Certified Large Lifting Beam
  • Full Ripout, Cutting new door frames size and make good
  • Installed lockable Hoardings for the duration of the project
  • Motor room and counterweight removal
  • Installation of large Storage Compound
  • Removal/Recycling of rubbish and debris as required

For further information regarding this project contact the ERS Project Team on 1300 747 688