Balmain Hospital

Lift Removal Full Ripout
Hospital
Overhead Traction
Liftronic
Balmain Hospital
ERS partnered with Liftronic in September 2020 to help with a Lift Replacement Project within Balmain Hospital – working in such a sensitive environment with tricky access always present a challenge
2

Total Lifts

10

Total Floors

Project Summary

Contractor – Liftronic
Project Manager – Keith Cavell
Project Site – Balmain Hospital
Project Date – September 2020
Project Scope Includes:

  • Complete Removal of 2×5 Stop OHT Lifts
  • Provide and Install Certified Lift Beam
  • Remove doors and frames
  • Installed lockable Hoardings for the duration of the project
  • Motor room and counterweight removal
  • Tricky access
  • Sensitive Operational Hospital
  • Removal/Recycling of rubbish and debris as required

For further information regarding this project contact the ERS Project Team on 1300 747 688