Pavilion on Northbourne, Canberra
Lift Removal Full Ripout
Project Type
Hotel & Accommodation
Industry
Overhead
Lift Type
KONE
Contractor
Pavilion on Northbourne
Client
In January 2013, ERS collaborated with Pavillion on Northbourne and KONE for a time-sensitive project involving the removal of a 1×3 stop overhead traction lift within the hotel.
1
Total Lifts
3
Total Floors
Project Summary
Contractors – Pavillion on Northbourne/KONE
Project Manager – Andrew Hoffman
Project Date – January 2013
Duration – 6 Days
Project Scope Includes:
- Provide & install large Hoardings
- Removal of 1×3 Stop Overhead traction Lift in hotel
- As well as removal of doors, door frames, sills and shot counter weight
- Removal/Recycling of rubbish and debris as required
For further information regarding this project contact the ERS Project Team on 1300 747 688