In December 2012, ERS collaborated with Grocon and Thyssenkrupp for a specialized project at 5 Martin Place, Sydney.
6

Total Lifts

72

Total Floors

Project Summary

Contractors – Grocon/Thyssenkrupp
Project Manager – Claudio Garcia
Project Date – December 2012
Duration – 6 Days
Project Scope Includes:

  • Provide & install Hoardings
  • Complex rigging
  • Drop lift car, counterweight and ropes into the pit and make safe 6 x 12 stops for demolition team

For further information regarding this project contact the ERS Project Team on 1300 747 688