450 Hunter St, Newcastle

Lift Removal
Commercial
Overhead Traction
KONE
ERS partnered with KONE in September 2015 for a renovation project, involving hoarding installation, equipment removal, concrete cutting, and more.
1

Total Lifts

5

Total Floors

Project Summary

Contractor – KONE
Project Site – 450 Hunter St, Newcastle
Project Date – September 2015
Project Scope Includes:

  • Complete Removal of 1×5 Stop OHT Lift
  • Provide and Install Certified Lift Beam
  • Removed doors and frames
  • Make good completed by onsite builder
  • Motor room and counterweight removal
  • Removal/Recycling of rubbish and debris as required

For further information regarding this project contact the ERS Project Team on 1300 747 688