105 Miller St, North Sydney

Lift Removal
Commercial
Hydro
OTIS
ERS partnered with OTIS Sydney in September 2013 for a modernisation project at 105 Miller St, North Sydney.
1

Total Lifts

2

Total Floors

Project Summary

Contractors – OTIS Sydney
Project Manager – Kevin McCreadie
Project Date – September 2013
Project Scope Includes:

  • Provide and Install hoardings
  • Removal of 1×2 stop Hydro
  • Doors and Frames to remain
  • Install working decks and beams
  • Run new mains from MR to service box
  • Concrete cutting service box
  • Removal of MR equipment
  • Removal/Recycling of rubbish and debris as required

For further information regarding this project contact the ERS Project Team on 1300 747 688