Macquarie Centre
Refurbishment
Project Type
Shopping Centre
Industry
Hydro
Lift Type
Westfield
Client
ERS worked with NASS/Westfields in April 2014 on a Macquarie Centre elevator upgrade. Tasks included: removing Hydro elevators, door and frame removal in an open shaft
2
Total Lifts
4
Total Floors
Project Summary
Contractors – NASS/Westfields
Project Manager – Rob Mitchell
Project Date – April 2014
Project Scope Includes:
- Removal of 2×8 stop Hydro
- Install a working platform on top of car in an open shaft
- Large scale Building/Demo Site
- Doors and Frames to be removed
- Remove 800L of oil from the Pitt
- Strip shaft and stainless steel flushings from the entire shaft
- Removal/Recycling of rubbish and debris as required
For further information regarding this project contact the ERS Project Team on 1300 747 688