In June and November 2013, ERS collaborated with OTIS Sydney for a substantial modernisation project.
3

Total Lifts

35

Total Floors

Project Summary

Contractors – OTIS Sydney
Project Manager – Kevin McCreadie
Project Date – June & November 2013
Project Scope Includes:

  • Provide and Install hoardings
  • Removal of 3×12 stop overhead
  • Doors and Frames to remain
  • Install working decks
  • Run new mains from MR to service box
  • Concrete cutting service box
  • Removal of MR equipment
  • Removal/Recycling of rubbish and debris as required