12 Moore St, Canberra – Mods – Motor Room Removal

MODS – Motor Room Removal
Commercial
Overhead Traction
Schindler
ERS was engaged to help on a tricky motor room removal for Schindler. From time to time when the Motor room has tricky access, no lifting beam or red flags our specialists teams will come onsite, remove the old and bring up the new
4

Total Lifts

Total Floors

Project Summary

Contractor – Schindler
Project Site – 12 Moore St, Canberra
Project Date – August 2015
Project Scope Includes:

  • Complete motor room removal of 4 Lifts
  • Bring new equipment up from the carpark to the motor room for Schindler
  • Removal/Recycling of rubbish and debris as required

For further information regarding this project contact the ERS Project Team on 1300 747 688